Meta PixelAnnual Audit Report 2024 — Municipality of Zamboanguita — Page 70

Page 70 of 125

Page 70
  12.6 The difference of 12.24 percent between the reported accomplishment and the
       verified accomplishment for the above project, corresponding to an amount of
       ₱146,864.77, is shown below:

                                                          Difference
                                                    Wt%          Amount
        Agency’s Reported Accomplishment             100       ₱ 1,200,000.00
        COA Verified Accomplishment                 87.76      ₱ 1,053,135.23
        Difference                                  12.24      ₱ 146,864.77

  12.7 It is worth mentioning that the deficiency noted during the inspection was
       incorporated into the final billing and has already been paid. As a result, the
       Municipality incurred an overpayment amounting to ₱146,864.77.

  12.8 The foregoing impairs the reliability of the completion reports submitted by the
       implementing office and raises concerns about the effectiveness of project monitoring
       and validation prior to payment. It also reflects lapses in internal controls, particularly
       in the verification and inspection processes, which may expose public funds to the
       risk of loss or misuse.

  12.9 We recommended and the Municipal Mayor and the Municipal Engineer agreed
       to inform the contractor of the deficiencies noted and require them to either
       perform the needed remedy works or refund the amount corresponding to the
       deficiency noted, totaling ₱146,864.77.

12.10 The Municipal Engineer explained that the discrepancy was due to a change in paint
      color during project implementation, as suggested by certain municipal officials.
      Management committed to try requesting a refund from the contractor. However, if
      the contractor refuses, the municipal officials will shoulder the cost of the refund if
      they are found to have caused the deficiency.

12.11 The Auditor would like to remind Management to strictly follow the approved plans
      and specifications during project implementation. If any changes are to be considered,
      prior approval should be sought.

LDRRMFIP

13. The Municipality's Local Disaster Risk Reduction and Management Council
    (LDRRMC) and the LDRRM Officer (LDRRMO) did not include in the CY 2024
    LDRRM Fund Investment Plan (LDRRMFIP) the list of projects and activities to be
    funded by the unexpended LDRRMF from prior years amounting to
    ₱12,143,559.77, which is inconsistent with COA Circular No. 2012-002 dated
    September 12, 2012, thereby risking delays in fund utilization during the year due to
    the absence of prior appropriation and approval.




                                                                                               61