Meta PixelAnnual Audit Report 2024 — City of Tanjay — Page 93

Page 93 of 111

Page 93
                                                                                              Status of
Ref               Observation                          Recommendations                    Implementation/
                                                                                         Results of Validation
No.    ₱10 million and spending                   charged to the correct fund            Council to properly
 11,   ₱6,998,414.02 for the purpose,             source, and ensure that the QRF is     plan the PPAs to be
page   despite the lack of an SP resolution       reserved for relief and recovery       undertaken, charged
 60    declaring a state of calamity,             programs      to    address    the      to the correct fund
       contrary to the NDRRMC-DBM-                immediate and short-term needs          source, and ensure
       DILG JMC No. 2013-1, hence                 of its people during calamities.          that the QRF is
       unnecessarily impairing the City’s                                                 reserved for relief
       ability to quickly respond to                                                          and recovery
       disasters had one occurred during                                                 programs to address
       the year, for which the fund was                                                   the immediate and
       primarily intended.                                                               short-term needs of
                                                                                           its people during
                                                                                               calamities.

                                              46) The LDRRM Council justify                  Unimplemented
                                                  charging the said project to the            Management
                                                  QRF for further evaluation in           commented that this
                                                  audit.                                 recommendation was
                                                                                               still unacted
                                                                                         considering a new set
                                                                                          of council members.
2022   The City Government had not            47) The City, through the LDRRMO,              Unimplemented
AAR,   finalized the Public Service               prioritize the finalization of the         The City had not
 AO    Continuity Plan (PSCP) as of               PSCP pursuant to NDRRMC                  finalized its PSCP.
 No.   December 31, 2022, as required in          Memorandum No. 33, s. 2018
 12,   the NDRRMC Memorandum Nos.                 immediately after the scheduled
page   33, s. 2018 and No. 57, s. 2020 due        training, especially since it is way
 62    to the absence of a duly-organized         past the October 2021 deadline
       working group to formulate the             set under CSC MC No. 12, s.
       plan as required in Section 5.0,           2021.
       Chapter II of the PSCP Guidebook
       and the lack of sufficient training    48) The City Mayor institutionalize          Unimplemented
       and knowledge regarding the                the PSCP by creating a working         Management is yet to
       proper formulation thereof, thus,          group that will perform the            conduct the training
       may significantly impair the               following activities:                   /workshop for the
       continuous delivery of quality                                                     PSCP Continuity
       essential services to the public           (a) Conduct a risk assessment;             Core Team.
       during an emergency, disaster, or          (b) Identify critical processes
       any disruptive event.                          and functions;
                                                  (c) Determine scenarios that
                                                      may       disrupt      normal
                                                      operation;
                                                  (d) Conduct risk analysis and
                                                      impact analysis;
                                                  (e) Formulate the PSCP based
                                                      on the identified risks on
                                                      critical    processes      and
                                                      functions and the related
                                                      steps to be followed to
                                                      eliminate, if not mitigate, the
                                                      impact of the determined
                                                      disruptions following the
                                                      prescribed templates and



                                                                                                             86