B. OTHER FINANCIAL RELATED ISSUES

  Unrecouped Advances to Contractors - ₱5,072,122.24

  2.    The City was not able to recouped advance payments made to contractors
       amounting to ₱5,072,122.24 for completed and terminated projects inconsistent
       with Section 4.2 of the Revised IRR of R.A. No. 9184, thus resulting to possible loss
       of government funds.
       2.1 The procuring entity is authorized to make an advance payment to the contractor
           in an amount not exceeding fifteen percent (15%) of the total contract price upon
           a written request of the contractor.

       2.2 Section 4.3 of Annex E of the Revised Implementing Rules and Regulations of
           R.A. No. 9184 provides that advance payment shall be repaid by the contractor
           by deducting fifteen percent (15%) from his periodic progress payments a
           percentage equal to the percentage of the total contract price used for the advance
           payment.

       2.3 As of December 31, 2024, the Advances to Contractors account has an
           outstanding balance of ₱5,987,659.11 (Appendix G). The audit disclosed that this
           balance pertains to 15% advance payments made in CYs 2020 and prior years and
           CYs 2022 to 2024, for projects that have either been completed, terminated or
           with unresolved right of way problems as reflected in the Report of Government
           Projects/Programs/Activities as of December 31, 2024, which was submitted by
           the City Engineer. The unrecouped amounts are listed below:

                                                                 Status per Report on
                        Particulars                   Amount      PPAs and Reply on
                                                                         Query
               15% Mobilization of 2CL             ₱147,225.00 Not in the report/ 100%
               Classrooms, Brgy. Mabunga                       Completed
               15% Mobilization of 2CL              226,500.00 Reverted/       Contract
               Classrooms, Brgy.                               Terminated
               Plagatsanon
               15% Mobilization of 2CL         ₱     54,959.00 Not in the report/ 100%
               Classrooms, Brgy. P.                            Completed
               Zamora
               Concreting of Brgy Road,             149,673.75 Not in the report/ 100%
               Brgy. Humayhumay                                Completed
               Concreting of Brgy Road,             149,673.75 Not in the report/ Contract
               Brgy. Hilaitan                                  Terminated
               Concreting of Brgy Road,             149,673.75 Not in the report/ 100%
               Brgy. Binobohan                                 Completed
               Imp. Of Multi-purpose Hall,           19,261.87 Not in the report/ Contract
               Brgy. Nagsaha                                   Terminated