Meta PixelAnnual Audit Report 2024 — City of Dumaguete — Page 69

Page 69 of 89

Page 69
                                                                              Status of
Reference           Observation             Recommendations               Implementation/
                                                                         Result of Validation
                                             the SEF property is
                                             made responsible for its
                                             proper       use      and
                                             accountability.
2022 AAR; Twenty buildings and           27. The CGSO prepare and        Not Implemented
AO No. 13;three hospitals/health             submit to the GSIS the
Page No.  centers with a total               Property       Inventory    Documentary
66        book       value     of            Form (PIF) listing all      requirements          for
          ₱3,613,849.79 were                 insurable properties to     insurance are not yet
          not insured with the               ensure that all insurable   complete. CGSO has
          GSIS, contrary to                  assets and properties are   requested      from   the
          Section 2 of RA No.                adequately insured with     Office of the Building
          656, as amended by                 the General Insurance       Official (OBO) and has
          P.D. No. 245 and COA               Fund to accord the city     yet    to     issue   the
          Circular No. 2018-                 with                some    occupancy permit, one of
          002, thereby exposing              indemnification in case     the required documents
          these properties to the            of damage or losses due     for property insurance.
          risk of having no                  to fortuitous events.
          indemnification      in
          case of loss.
2021 AAR; The Petty Cash Fund            28. Management sees to it Not Implemented
AO No. 1; (PCF) amounting to                 that the guidelines on
Page No. ₱36,211.32 was not                  PCF      are    strictly Management has yet to
45        fully liquidated at the            observed.                follow fully the imprest
          end of the year                                             system as of December
          contrary to Section 48                                      31, 2024.
          of       the      New
          Government
          Accounting      System
          (NGAS) Manual for
          LGUs, Volume 1.

2021          The accuracy and           29. The            Inventory    Not Implemented
AAR; AO       reliability of the Road        Committee conduct an
No. 4; Page   Networks         account       annual physical count of    This               audit
No. 54        totaling                       all LRN and the results     recommendation        is
              ₱52,984,887.52 could           thereof reported in the     restated/revised in CY
              not be ascertained due         RPCLRN          to    be    2024 (AO No. 2, Page
              to: (a) non-conduct of         submitted to the Auditor    No. 53).
              inventory of local             and Accounting unit not     .
              roads      and      non-       later than January 31 of
              preparation of the             each       year.    The
              Report on the Physical         RPCLRN        shall   be
              Count of Local Road            reconciled with the
              Network (RPCLRN);              accounting records, and
              (b) non-maintenance            the necessary adjusting
              of the Local Road              entries are prepared
              Network Ledger Card            before the statement
              (LRNLC) and Local              date.
              Road            Network

                                                                                                     96