                                                                               Management                     Status of
  Ref.              Observation                  Recommendations
                                                                            Comments/Actions               Implementation
                                                                            4.     Recovery   and
                                                                               Rehabilitation
                                                                               Services
2018 AAR,   The Municipality has not        44. We recommended that the CBMS had been established           Implemented
AO No. 9,   established or set up a Gender      Municipal Mayor require and maintained.
 page 47    and Development database to         the Municipal Planning
            serve as basis for gender-          and Development Officer
            responsive           planning,      to establish and maintain
            programming and policy              a GAD database in order
            formulation as required under       to provide the data
            Section 36 (c) of R.A. 9710,        necessary to properly
            nor establish a GAD                 plan GAD projects and
            Monitoring and Evaluation           activities.
            (M&E) System as required
            under Secs. 3.4 and 5.1 of 45. We further recommended            A         gender-responsive    Implemented
            PCW-DILG-DBM-NEDA                  that the municipal mayor      monitoring and evaluation
            Joint Memorandum Circular          create      a       gender-   system had been created and
            No. 2013-01, which could           responsive Monitoring         maintained.
            adversely affect the direction     and Evaluation System in
            of its GAD policies and            order that GAD projects
            programs and hinder the            and activities are properly
            assessment of the success or       planned and implemented
            failure thereof.                   and its results assessed to
                                               ensure its success.
2017 AAR,   Excessive      quantities   of 46. We recommended that           POWs had not been attached    Unimplemented
AO No. 4,   materials were programmed          Program of Work be            to the DVs.
 page 34    for the improvement of three       properly prepared based
            day care centers under the         on detailed engineering
            Bottom-up           Budgeting      measurements,          duly
            program of the national            reviewed        by      the


                                                                                                                            68