       aforementioned guidelines and Section 2.1 of COA Circular No. 2012-001 dated
       June 14, 2012, was likewise not provided.

15.5   Our inquiry with the Provincial Budget Officer on the procedures for inclusion
       of financial assistance to NGOs in the Annual Budget revealed that accredited
       NGOs/POs submit their proposal to the Provincial Development Council (PDC)
       for inclusion in the Annual Investment Program (AIP) and, if approved, in the
       Annual Budget at a fixed amount of ₱500,000.00 for each NGO/PO.

15.6   The absence of required documentation and proper publication of priority
       projects can have an impact on transparency and accountability in grant
       allocation. Without a list of priority projects and published information, the
       public may not have a clear understanding of project priorities or the intended
       use of funds, which could compromise the effectiveness of the financial
       assistance provided to NGOs/POs.

Insufficient documentation to confirm compliance with RA No. 9184

15.7   Section 4.5.2 of the Circular requires that for each project proposal, the GO shall
       accredit the NGO/PO project partners through the Bids and Awards Committee
       (BAC), which shall perform the selection criteria, including the screening of the
       qualification documents, ocular inspection of the NGOs/POs business site, and
       the evaluation of the technical and financial capability of the NGO/PO.

15.8   Further, Section 4.5.3 thereof states that upon proper evaluation, the GO, thru
       the Committee, shall award the project to the NGO/PO that meets the minimum
       qualification requirements and the specifications for the project and which can
       satisfactorily undertake the project at terms most advantageous to the
       beneficiaries taking into consideration the cost effectiveness of the project.

15.9   However, proof of accreditation of the NGO/PO by the BAC and the results of
       the evaluation of the financial and technical capability of the selected NGO/PO
       were not submitted or attached to the DV in support of the grant.

15.10 Further, the NGO/POs project proposals for funding were not accompanied by
      the following requirements under Section 4.4 of COA Circular No. 2007-001:

       a. Authenticated copy of the latest Articles of Incorporation, or the
          Articles of Cooperation, as the case may be, showing the original
          incorporators/organizers and the Secretary’s certificate for
          incumbent officers, together with the Certificate of Filing with the
          Securities and Exchange Commission (SEC) or Certificate of
          Approval by the Cooperative Development Authority (CDA);
       b. Audited financial reports for the past three years preceding the date
          of project implementation. For NGO/PO which has been in
          operation for less than three years, financial reports for the years in
          operation and proof of previous implementation of similar projects;
       c. Disclosure of other related business, if any;
       d. Work and Financial Plan (WFP) and sources and details of
          proponent’s equity participation in the project;

                                                                                       79