Meta PixelAnnual Audit Report 2024 — Municipality of Zamboanguita — Page 66

Page 66 of 125

Page 66
   10.3 Furthermore, as indicated on the Certificate of Final Inspection and Completion dated
        March 6, 2023, signed by the Municipal Engineer and Municipal Mayor, the project
        was reported to have been completed in accordance with the technical engineering
        specifications set forth in the contract documents.

   10.4 However, an ocular inspection conducted by the COA Technical Audit Specialist
        (TAS) on November 4, 2024, revealed that the project was only 97.22 percent
        complete, contrary to the 100 percent completion stated in the Certificate of Final
        Inspection and Completion dated March 6, 2023, prepared by Management. The
        discrepancy between the reported and verified accomplishments is detailed in the
        table on the following page:

    Work Items Involved      Agency’s Reported Accomplishment    COA Verified Accomplishment
                                                          %               %
        Description              Amount        Wt% Completed     Wt% Completed     Amount
A. Other General Requirement
  A.1   Occupational Safety
        & Health Program        ₱ 22,500.00 0.739       100%     0.739    100%     ₱      22,500.00
  A.2   Project Billboard/
        Signboard               ₱    4,312.50 0.142     100%     0.142    100%     ₱       4,312.50
  A.3   Mobilization/
        Demobilization          ₱ 15,000.00 0.493       100%     0.493    100%     ₱      15,000.00
B. Earthworks
100(1) Clearing & Grubbing      ₱    7,125.00 0.234     100%     0.234    100%     ₱       7,125.00
  102   Roadway Excavation
        Works                   ₱ 40,077.00 1.316       100%     1.316    100%     ₱      40,077.00
  105   Sub-grade
        Preparation Works       ₱ 24,000.00 0.788       100%     0.788    100%     ₱      24,000.00
C. Base Course
 201    Aggregate Base
        Course Works            ₱ 488,523.00 16.044     100%     16.044   100%     ₱ 488,523.00
D. Surface Course
 311    Portland Cement
        Concrete Pavement
        Works                  ₱ 2,443,282.86 80.244    100%     77.466   96.54%   ₱ 2,358,707.68
Total                          ₱ 3,044,820.36   100               97.22            ₱ 2,960,245.18

   10.5 The inspection report from the COA Technical Audit Specialist (TAS) for the above
        project stated that during the inspection, four blocks with longitudinal cracks were
        observed on the left lane, with a corresponding cost of ₱84,575.18, which was not
        included in the COA Verified Accomplishment.

   10.6 The difference of 2.78 percent between the reported accomplishment and the verified
        accomplishment for the above project, corresponding to an amount of ₱84,575.18, is
        shown below:

                                                                  Difference
                                                         Wt%              Amount
              Agency’s Reported Accomplishment            100            ₱ 3,044,820.36
              COA Verified Accomplishment                97.22           ₱ 2,960,245.18
              Difference                                 2.78            ₱    84,575.18

                                                                                               57