13.2. Verification conducted by the Audit Team on the Municipality’s compliance with
      the above provision yielded the following results:

Non-monitoring on furnishing of the SEF Annual Budget for CY 2024 to the
Municipal Treasurer, Municipal Budget Officer, and Municipal Accountant within
the indicative timeline of not later than seven days after approval.

13.3. A phone inquiry with the District Supervisor revealed that the LSB was able to
      furnish the Municipal Budget Officer, Municipal Accountant, and Municipal
      Treasurer with a copy of the approved CY 2024 SEF Budget. However, no formal
      transmittal letter was prepared to document the date of receipt. Although the
      concerned offices received their respective copies, no date of receipt was indicated,
      and there was no documentation confirming whether the transmittal was made
      within the prescribed timeline.

Non-submission of quarterly and annual reports using the SEF Budget
Accountability Form No. 1 on SEF Utilization

13.4. A phone inquiry with the Municipal Accountant revealed that the SEF Utilization
      reports prepared by their office were not submitted on a quarterly and annually
      basis to the Regional Offices of the DBM and the DILG, nor were copies furnished
      to the Sangguniang Bayan, as required.

13.5. Also, an inquiry with the District Supervisor disclosed that the SEF Utilization
      Report was forwarded to the DepEd Central Office through an online submission
      link, in accordance with the instructions directing field offices to transmit reports
      via their Division Focal Person. However, no documentation or transmittal receipt
      was provided to the Audit Team to verify the actual date and proof of submission.

Non-compliance with the required posting of the SEF Utilization Report

13.6. The Municipality designated Full Disclosure Policy (FDP) Bulletin Boards for the
      posting of SEF Utilization Reports, located at the Municipal Hall Building, in front
      of Parish of Our Lady of the Abandoned Church, and in the Municipal Public
      Market. While it was verified that the reports were uploaded to the DILG FDP
      Portal, the latest report posted on the bulletin boards was only for the 2nd Quarter
      of 2024. There was no physical posting of the 3rd Quarter SEF Utilization Report
      on any of the bulletin boards.

13.7. Overall, the LSB did not fully comply with all the required activities under Item
      6.1 of DepEd-DBM-DILG JC No. 1, series of 2017, thereby hindering the
      attainment of the national objective of promoting and enhancing transparency and
      accountability in the allocation and utilization of the SEF.