                 2) January-February - All LGU departments/offices including
                     barangays shall formulate their GAD AR of the preceding
                     year. Based on its accomplishments in the preceding year and
                     the results of the conduct of gender analysis to determine the
                     existing gender issues of the locality, the LGU
                     departments/offices shall prepare its GPB proposal for the
                     succeeding year for submission to the LGU GAD Focal Point
                     System (GFPS). The LGU GFPS Technical working Group
                     (TWG) shall review and consolidate the inputs submitted by
                     the LGU departments/offices for the preparation of the LGU
                     GPB and GAD AR.

                 3) March - The consolidated GPBs, together with the GAD ARs,
                    shall be submitted to the City/Municipal Planning
                    Development office (C/MPDO) in the case of barangays; and
                    to the Provincial Planning Development office (PPDO) in the
                    case of component cities and municipalities to ensure the
                    alignment of the GAD PPAs of the concerned LGU to the
                    priorities of the LGU exercising jurisdiction over it.
                    Afterwards, the GPBs shall be submitted not later than March
                    31 to the DILG City/Municipal Local Government Operations
                    Officer (C/MLGOOI) in the case of barangays, and the DILG
                    Provincial Office in the case of component cities and
                    municipalities for review and endorsement.”

12.3. During our audit of the Municipality’s GAD Programs, we noted that the
       Municipality submitted its FY 2024 GPB to the Provincial Planning and
       Development Office (PPDO) only on September 13, 2024. This submission
       contravenes the aforementioned regulations, which requires the GFPS TWG to
       submit the consolidated GPBs and the GAD ARs to the PPDO by March 2023 and
       not later than March 31, 2023, to the DILG Provincial Office.

12.4. Since the Municipality did not submit the GPB to the PPDO within the designated
       timeframe, the PPDO was unable to conduct a timely review of its FY 2024 GPB to
       ensure that its GAD PPAs align with the priorities of the Provincial Government.
       Additionally, the Municipality’s failure to submit the GPB to the DILG Provincial
       Office also prevented a timely review and endorsement, making it impossible to
       guarantee the gender-responsiveness of the PPAs in the GPB.

12.5. On the other hand, Section C.8 (5) of the PCW-DILG-DBM-NEDA JMC
       No. 2013-01 states that the annual GAD AR must be accompanied by the following:
       (1) a brief summary of the reported program or project; (2) copies of reported policy
       issuances; (3) results of HGDG tests; and (4) actions taken by the LGU on the COA
       audit findings and recommendations.