The Supreme Court took up consolidated petitions filed by the Energy Regulatory Commission (ERC) and the Manila Electric Company (MERALCO) challenging a Court of Appeals (CA) decision that invalidated ERC orders substituting regulated prices for market-determined Wholesale Electricity Spot Market (WESM) prices during the supply months of November and December 2013. The cases required the Court to determine the constitutional and statutory boundaries governing the ERC's power to intervene and regulate electricity market prices.
The Case
The consolidated Petitions for Review on Certiorari were filed under Rule 45 of the Rules of Court by the ERC and MERALCO. They challenged the CA Decision dated November 7, 2017, and the Omnibus Resolution dated March 29, 2019.
According to the decision, Republic Act No. 9136, known as the Electric Power Industry Reform Act of 2001 (EPIRA), restructured the Philippine electric power industry into four sectors: generation, transmission, distribution, and supply. The generation and supply sectors are envisioned as competitive markets driven by free market dynamics, while transmission and distribution are classified as regulated natural monopolies subject to oversight by the ERC.
The EPIRA mandated the establishment of the WESM, which operates as a gross pool market where electricity is traded as a commodity and prices are determined primarily by the dynamics of supply and demand. Under the WESM Rules, power generation companies (GenCos) are obligated to offer their maximum available capacity into the market, subject only to limited and justified exceptions—a mandate commonly referred to as the "Must Offer Rule."
In the assailed Decision, the CA favored the position of the GenCos, principally represented by San Miguel Energy Corporation, invalidating four ERC Orders that substituted regulated prices for market-determined WESM prices during November and December 2013. The CA ruled that the ERC acted without or beyond its jurisdictional authority, rendering the contested ERC Orders null and void, and mandating a reversion to the original WESM-cleared prices for the contested period. Through its Omnibus Resolution, the CA denied the separate Motions for Reconsideration filed by the ERC and MERALCO.
The Issue
The Court framed the controversy as the scope and limits of the regulatory authority exercised by the ERC over the WESM, particularly during periods characterized by extraordinary market conditions. The resolution of the case required a determination of whether the ERC's actions were consistent with statutory directives, supported by substantial evidence, and executed in a manner that respects fundamental constitutional principles.
The Ruling
The decision states that the ERC's finding that the prevailing WESM prices were not reasonable, rational, or competitive was not the product of a formal inquiry, but merely a conclusory assertion that rested on preliminary observations never tested in a contested proceeding. The result, the decision states, was a regulatory determination devoid of evidentiary anchorage, contrary to the fundamental requirement that administrative decisions be supported by substantial evidence.
The decision further states that the ERC's actions contravened its own procedural rules under the Implementing Rules and Regulations (IRR) of the EPIRA. Rule 3, Section 4(e) of the IRR allows distribution utilities such as MERALCO to pass through generation charges to consumers under the Automatic Generation Rate Adjustment (AGRA) mechanism, subject to post-verification and confirmation by the ERC.
By the Numbers
- G.R. Nos. 246621-30 and 247352-61
- CA Decision dated November 7, 2017
- Omnibus Resolution dated March 29, 2019
- Four ERC Orders invalidated by the CA
- Supply months of November and December 2013
- Republic Act No. 9136 (EPIRA)
- The ERC may grant provisionally or deny relief not later than 75 calendar days from the filing of the application or petition
- Comments or pleadings may be filed within 30 calendar days from receipt of a copy of the application or petition or from publication
The Court's Reasoning
The decision emphasizes the requirement that an administrative tribunal must consider the evidence presented, citing that the right to adduce evidence, without the corresponding duty on the part of the board to consider it, is vain. It explains that while the duty to deliberate does not impose the obligation to decide right, it does imply a necessity that cannot be disregarded—that of having something to support a decision.
The decision reiterates that not only must there be some evidence to support a finding or conclusion, but the evidence must be "substantial." It defines substantial evidence as such relevant evidence as a reasonable mind accept as adequate to support a conclusion, and states that mere uncorroborated hearsay or rumor does not constitute substantial evidence.
The decision also states that a decision must be rendered on the evidence presented at the hearing or at least contained in the record and disclosed to the parties affected, so that the parties can be protected in their right to know and meet the case against them. Applying these principles, the decision found that the ERC's determination lacked evidentiary anchorage and contravened both statutory requirements and the ERC's own procedural rules under the IRR of the EPIRA.
Source: Supreme Court decision in G.R. Nos. 246621-30 and 247352-61.
This report summarizes a public Supreme Court decision and is not legal advice.